Sykesville firehouse rebuild heads into phase two

 
By Heather Rudow, Advocate Staff Writer
April 20, 2011
 

Sykesville-Freedom District Fire Department's members finally have a solid place to rest their heads, after spending more than a year living out of tents and trailers when a devastating fire destroyed most of their firehouse Feb. 11 last year. Members were able to move into the first finished portion of what will eventually be a 32,000-square foot building a couple of weeks ago, which includes 12 bunk rooms, a temporary day room and kitchen as well as bathrooms.

Brian Bowman, chairman of the Sykesville-Freedom District Fire Department's building committee, said transferring everything into the new location was a team effort.

"The move went super," he said. "We had a lot of people showing up and asking, 'What can I do to help?' It was 100 percent cooperation from paid people and volunteers."

Member Tim Matthews spent the first night in the new building, and he said it is a step up from what the firefighters have been living in during the past year.

"It's really good to have a comfortable bed and room all to yourself," he said. "When we were in the trailers, it was community rooms without any privacy. Now, we have individual bathrooms and showers."

Bowman said the new firehouse and social hall are being built with the future of the community and the fire department itself in mind.

"The rule of this is that the hall and everything will be coming in at 45 percent bigger," he said.

The old building and banquet hall were a combined 16,477 square feet before the fire. The old banquet hall could only seat 275, whereas the new one will have a 400-person capacity, and the ability to be split into two, 200-person banquet halls.

Sykesville-Freedom District Fire Department President Kevin Shiloh said the total cost of the first phase was almost $1 million, which was paid for through insurance money. He said the entire building is quoted to cost approximately $5.5 million, but it is too early in the rebuilding process to say for certain.

Along with being much larger, the building will also be more technologically advanced. Each of the bunk rooms has a volume knob that allows members turn down the scanner chatter while they sleep, but will automatically turn up as soon as Sykesville gets a call.

"It's no more of this banging on walls to tell people that we've got a call," Bowman said.

There will also be four extra bays for the firehouse's engine bay to put its ambulance and Emergency Medical Services equipment, which Bowman said will help differentiate them from the fire equipment.

"A lot of thought was put into this," Bowman said. "I'm proud of this. I really am."

The second and final phase of the rebuilding process will include the construction of eight more bunk rooms, common rooms, training rooms, a kitchen, administrative offices and banquet hall.

Dave Woodward of Manns Woodward, the architecture firm in charge of the rebuilding project, said it will take approximately one year to complete phase two once they start breaking ground.

"We are working on getting the building permit plans done by the end of this month to the beginning of next month," he said.

Along with building permit plans, Woodward said, the firm must also get site plans approved. He said they have been attending public meetings to get the plans for the past five months. However, he said, because it is a lengthy process which requires the firm to resubmit new plans after each meeting, when they can actually begin construction remains to be seen.

"It's hard to say," Woodward said, "because the site development plan is such a back-and-forth process. I couldn't even begin say."

Reach Staff Writer Heather Rudow at 410-857-3317 or heather.rudow@eldersburgadvocate.com.